Schönbek, Germany, 9000 KWp

Completion date: March, 2021

Power: 9000 KWp

Scope of services: Complete mechanical installation including pile driving

 

Project Nr. 192 with a 9MW power output was installed in Schonbek – Germany  in March 2021. The development of the installation took 20 Days.  Together 20 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical photovoltaics installation. 9 MW of pile driving, 4MW of frame assembly and modules installation.

Galéria:

Similar projects

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.