Project Nr. 304
Location: Wiernsheim, Germany
Completion date: January, 2023
Power: 10000 KWp
Scope of services: complete mechanical installation
Project Nr. 304 with a 10000 KWp power output was installed in Germany. Assembly works were finished in January 2023. The development of the installation took 10 weeks. Together 25 experienced engineers were part of the installation process. Mounting system was from Zimmermann.
Solar Company has provided the complete mechanical installation incl. GAYK pile driving.