Project Nr. 304

Lokalita: Wiernsheim, Germany

Dátum ukončenia: January, 2023
Výkon: 10000 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.

Project Nr. 304 with a 10000 KWp power output was installed in Germany. Assembly works were finished in January 2023. The development of the installation took 10 weeks.  Together 25 experienced engineers were part of the installation process. Mounting system was from Zimmermann.

Solar Company has provided the complete mechanical installation incl. GAYK pile driving.

 

 

 

 

 

 

 