Project Nr. 351
Lokalita: Dobele, Latvia
Dátum ukončenia: December, 2023
Výkon: 2500 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.
Project Nr. 351 with a 2500 KWp power output was installed in Latvia. Assembly works were finished in 4Q 2023. The development of the installation took 3 weeks. Together 12 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation of CORAB frame system including pile driving with GAYK HRE3000