Project Nr. 351

Location: Dobele, Latvia

Completion date: December, 2023
Power: 2500 KWp
Scope of services: Complete mechanical installation, including pulling of DC cables.

Project Nr. 351 with a 2500 KWp power output was installed in Latvia. Assembly works were finished in 4Q 2023. The development of the installation took 3 weeks.  Together 12 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical installation of CORAB frame system including pile driving with GAYK HRE3000

 

 

 

 

 

 

 

Request a price offer info@solarcompany.sk