Project Nr. 320
Lokalita: Unterbinnwang, Germany
Dátum ukončenia: April, 2023
Výkon: 4800 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.
Project Nr. 320 with a 4800 KWp power output was installed in Germany. Assembly works were finished in 2Q 2023. The development of the installation took 4 weeks. Together 20 experienced engineers were part of the installation process. The mounting system was from SL Rack GmbH.
Solar Company has provided the mechanical installation including pile driving with GAYK HRE 3000