Project Nr. 319
Lokalita: Eisenberg, Germany
Dátum ukončenia: May, 2023
Výkon: 8000 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.
Project Nr. 319 with a 8000 KWp power output was installed in Germany. Assembly works were finished in 2Q 2023. The development of the installation took 7 weeks. Together 22 experienced engineers were part of the installation process. The mounting system was from Zimmermann.
Solar Company has provided the mechanical installation including pile driving with GAYK HRE 3000