Project Nr. 301
Lokalita: Richthof , Germany
Dátum ukončenia: December, 2022
Výkon: 11000 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.
Project Nr. 301 with a 11000 KWp power output was installed in Germany. Assembly works were finished in December 2022. The development of the installation took 8 weeks. Together 30 experienced engineers were part of the installation process. Zimmermann system was used for this solar park.
Solar Company has provided the complete mechanical installation incl. GAYK pile driving.