Project Nr. 345

Lokalita: Heiterbach , Germany

Dátum ukončenia: December, 2023
Výkon: 10600 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.

Project Nr. 345 with a 10600 KWp power output was installed in Germany. Assembly works were finished in 1Q 2024. The development of the installation took 12 weeks.  Together 24 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical installation of Arausol frame system including pile driving with GAYK HRE3000

 

 

 

 

 

 

 