Project Nr. 298

Lokalita: Vellberg, Germany

Dátum ukončenia: December, 2022
Výkon: 5000 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.

Project Nr. 298 with a 5000 KWp power output was installed in Germany. Assembly works were finished in December 2022. The development of the installation took 5 weeks.  Together 25 experienced engineers were part of the installation process. Hemma Rack  system was used for this solar park.

Solar Company has provided the complete mechanical installation incl. pile driving with GAYK

 

 

 

 

 

 

 