Project Nr. 297

Lokalita: Landershausen, Germany

Dátum ukončenia: December, 2022
Výkon: 7300 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.

Project Nr. 297 with a 7300 KWp power output was installed in Germany. Assembly works were finished in December 2022. The development of the installation took 7 weeks.  Together 30 experienced engineers were part of the installation process. Meiser system was used for this solar park.

Solar Company has provided the complete mechanical installation incl. pile driving with GAYK

 

 

 

 

 

 

 