Project Nr. 342
Riga,
Latvia,
5000 KWp
Completion date: October, 2023
Power: 5000 KWp
Scope of services: complete mechanical installation including pile driving
Project Nr. 342 with a 5000 KWp power output was installed in Latvia. Assembly works were finished in 3Q 2023. The development of the installation took 5 weeks. Together 16 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation of Corab frame system including pile driving with GAYK HRE3000