Project Nr. 238

Project Nr. 238

Abensberg, Germany, 1900 KWp

Completion date: December, 2021

Power: 1900 KWp

Scope of services: Complete mechanical installation including pile driving

 

Project Nr. 238 with a 1,9 MW power output was installed in Germany – and finished in January 2022. The development of the installation took 20 days.  Together 12 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical installation incl. pile driving with piling rig GAYK HRE 3000

 

 

 

 

 

 

 

Galéria:

Similar projects

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.