Project Nr. 365
Location: Perl, Germany
Completion date: March, 2024
Power: 11000 KWp
Scope of services: Complete mechanical installation, including pulling of DC cables.
Project Nr. 365 with a 11000 KWp power output was installed in Germany. Assembly works were finished in 1Q 2024. The development of the installation took 12 weeks. Together 25 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation of Zimmerman Gmbh frame system including pile driving with GAYK HRE 3000