Project Nr. 336
Location: Picheldorf, Austria
Completion date: May, 2023
Power: 2500 KWp
Scope of services: complete mechanical installation including pile driving
Project Nr. 336 with a 2500 KWp power output was installed in Austria. Assembly works were finished in 2Q 2023. The development of the installation took 4 weeks. Together 16 experienced engineers were part of the installation process.
Solar Company has provided the mechanical installation including pile driving with GAYK HRE3000