Project Nr. 332

Location: Trofaiach, Austria

Completion date: August, 2023
Power: 6300 KWp
Scope of services: complete mechanical installation including pile driving

Project Nr. 332 with a 6300 KWp power output was installed in Austria. Assembly works were finished in 3Q 2023. The development of the installation took 8 weeks.  Together 25 experienced engineers were part of the installation process. Construction system was from Alumero..

Solar Company has provided the mechanical installation including pile driving with GAYK HRE3000

 

 

 

 

 

 

 

Request a price offer info@solarcompany.sk