Project Nr. 329
Location: Cloppenburg, Germany
Completion date: June, 2023
Power: 6600 KWp
Scope of services: complete mechanical installation
Project Nr. 329 with a 6600 KWp power output was installed in Germany. Assembly works were finished in 2Q 2023. The development of the installation took 10 weeks. Together 20 experienced engineers were part of the installation process. Construction system was from SL Rack GmbH.
Solar Company has provided the mechanical installation including drilling.