Project Nr. 318
Location: Gunzburg, Germany
Completion date: April, 2023
Power: 7200 KWp
Scope of services: complete mechanical installation including pile driving
Project Nr. 318 with a 7200 KWp power output was installed in Germany. Assembly works were finished in 2Q 2023. The development of the installation took 7 weeks. Together 18 experienced engineers were part of the installation process. The mounting system was from Zimmermann.
Solar Company has provided the mechanical installation including pile driving with GAYK HRE 3000