Project Nr. 313
Location: Dietenhofen, Germany
Completion date: March, 2023
Power: 3600 KWp
Scope of services: complete mechanical installation including pile driving
Project Nr. 313 with a 3600 KWp power output was installed in Germany. Assembly works were finished in March 2023. The development of the installation took 3 weeks. Together 20 experienced engineers were part of the installation process. The mounting system was from Zimmermann E/W
Solar Company has provided the mechanical installation incl. GAYK pile driving.