Project Nr. 296

Location: Wittenberg, Germany

Completion date: December, 2022
Power: 7000 KWp
Scope of services: complete mechanical installation

Project Nr. 296 with a 7000 KWp power output was installed in Germany. Assembly works were finished in December 2022. The development of the installation took 7 weeks.  Together 20 experienced engineers were part of the installation process. Zimmermann system was used for this solar park.

Solar Company has provided the complete mechanical installation incl. pile driving with GAYK

 

 

 

 

 

 

 