Project Nr. 287
Location: Ochoz, Czech Republic
Completion date: October, 2022
Power: 1900 KWp
Scope of services: complete mechanical installation
Project Nr. 287 with a 1900 KWp power output was installed in Czech Republic. Assembly works were finished in October 2022. The development of the installation took 14 days. Together 10 experienced engineers were part of the installation process. Arausol mounting system was used for this solar park.
Solar Company has provided the complete mechanical installation incl. pile driving with GAYK