Project Nr. 279

Location: Baiersdorf, Germany

Completion date: October, 2022
Power: 4700 KWp
Scope of services: complete mechanical installation

Project Nr. 279 with a 4700 KWp power output was installed in Germany. Assembly works were finished in October 2022. The development of the installation took 5 weeks.  Together 16 experienced engineers were part of the installation process. SL Rack mounting system was used for this solar park.

Solar Company has provided the complete mechanical installation incl. pile driving

 

 

 

 

 

 

 

Request a price offer info@solarcompany.sk
This is default text for notification bar