Project Nr. 277
Location: Viechtach, Germany
Completion date: November, 2022
Power: 8300 KWp
Scope of services: complete mechanical installation
Project Nr. 277 with a 8300 KWp power output was installed inGermany. Assembly works were finished in November 2022. The development of the installation took 2 months. Together 14 experienced engineers were part of the installation process. SL Rack mounting system was used for this solar park.
Solar Company has provided the complete mechanical installation incl. pile driving