Project Nr. 268
Location: Weimar, Germany
Completion date: August, 2022
Power: 2300 KWp
Scope of services: complete mechanical installation including pile driving
Project Nr. 268 with a 2,3 MWp power output was installed in Germany. Assembly works were finished in August 2022. It was a combination of PEG system and a standard south frame from SL Rack. The development of the installation took 3 weeks. Together 12 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation incl. pile driving