Project Nr. 262
Location: Meinburg, Germany
Completion date: June, 2022
Power: 6500 KWp
Scope of services: Complete mechanical installation including pile driving
Project Nr. 262 with a 6,5 MWp power output was installed in Germany. Assembly works were finished in June 2022. The development of the installation took 5 weeks. Together 18 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation incl. pile driving