Project Nr. 257

Location: Handelsleben, Germany

Completion date: May, 2022
Power: 4700 KWp
Scope of services: Complete mechanical installation including pile driving

Project Nr. 257 with a 4,75 MWp power output was installed in Germany. Pile driving and frame assembly were finished in May 2022, and modules installation in August to modules missing.  The development of the installation took 6 weeks.  Together 22 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical installation incl. pile driving

 

 

 

 

 

 

 

Request a price offer info@solarcompany.sk
This is default text for notification bar