Project Nr. 236

Location: Simmelsdorf, Germany

Completion date: December, 2021
Power: 10000 KWp
Scope of services: Complete mechanical installation including pile driving

Project Nr. 236 with a 10MW power output was installed in Germany – and finished in December 2021. The development of the installation took 2 months.  Together 25 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical installation incl. pile driving with two machines GAYK HRE 3000

 

 

 

 

 

 

 