Project Nr. 228

Location: Eggebek , Germany

Completion date: October, 2021
Power: 11000 KWp
Scope of services: Complete mechanical installation including pile driving

Project Nr. 228 was installed in Eggebek – Germany and finished in October 2021. The development of the installation took 6 weeks .  Together 25 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical installation on 11MW part and 25MW pile driving.

Mounting system is from company Enerpark.

 

 

 

 

 

 