Project Nr. 203
Location: Spielberg, Austria
Completion date: June, 2021
Power: 438 KWp
Scope of services: Solar Company has provided the complete mechanical installation incl. DC
Project Nr. 203 with a 438 KW power output was installed in Spielberg – Austria in Jun 2021. The development of the installation took 7 days. Together 6 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation incl. DC