Project Nr. 194
Location: Pforzen, Germany
Completion date: April, 2021
Power: 1000 KWp
Scope of services: Complete mechanical installation including pile driving
Project Nr. 194 with a 1 MW power output was installed in Pforzen – Germany in April 2021. The development of the installation took 4 Days. Together 6 experienced engineers were part of the installation process.
Solar Company has provided the mechanical photovoltaics installation of pile driving and frame assembly. Modules were made by another company due to components delay.
Frame manufacturer was Pradecon- Portugal.