Project Nr. 354
Lokalita: Tierberg, Germany
Dátum ukončenia: December, 2023
Výkon: 5200 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.
Project Nr. 354 with a 5200 KWp power output was installed in Germany. Assembly works were finished in 4Q 2023. The development of the installation took 4 weeks. Together 21 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation of Arausol Technik frame system including pile driving with GAYK HRE 3000