Project Nr. 347

Lokalita: Mindelstetten, Germany

Dátum ukončenia: December, 2024
Výkon: 10500 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.

Project Nr. 347 with a 10500 KWp power output was installed in Germany. Assembly works were finished in 4Q 2023. The development of the installation took 8 weeks.  Together 30 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical installation of MKG Gobel frame system including pile driving with GAYK HRE3000

 

 

 

 

 

 

 