Project Nr. 310
Lokalita: Lazinky, Czech Republic
Dátum ukončenia: March, 2023
Výkon: 3850 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.
Project Nr. 310 with a 3850 KWp power output was installed in Czech Republic. Assembly works were finished in March 2023. The development of the installation took 3 weeks. Together 20 experienced engineers were part of the installation process. The mounting system was from Arausol Gmbh.
Solar Company has provided the mechanical installation incl. GAYK pile driving.