Project Nr. 266

Lokalita: Geierstal, Germany

Dátum ukončenia: July, 2022
Výkon: 3000 KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.

Project Nr. 266 with a 3 MWp power output was installed in Germny. Assembly works were finished in July 2022.  The development of the installation took 3 weeks.  Together 18 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical installation incl. pile driving

 

 

 

 

 

 

 