Project Nr. 231
Lokalita: Punitz, Austria
Dátum ukončenia: November, 2021
Výkon: 3300KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.
Project Nr. 231 with a 3300 KW power output was installed in Punitz – Austria and finished in November 2021. The development of the installation took 30 days . Together 15 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation incl. pile driving and AC+DC work.
Solar structure used was Meiser Solar