Project Nr. 231

Lokalita: Punitz, Austria

Dátum ukončenia: November, 2021
Výkon: 3300KWp
Rozsah služieb: Kompletná inštalácia vrátane ťahania káblov prúdu.

Project Nr. 231 with a 3300 KW power output was installed in Punitz – Austria and finished in November 2021. The development of the installation took 30 days .  Together 15 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical installation incl. pile driving and AC+DC work.

Solar structure used was Meiser Solar

 

 

 

 

 

 

 

Získajte cenovú ponuku info@solarcompany.sk
This is default text for notification bar