Project Nr. 217

Project Nr. 217

Schopfloch, Germany, 3200 KWp

Completion date: October, 2021

Power: 3200 KWp

Scope of services: Complete mechanical installation including pile driving

 

Project Nr. 217 with a 3200 KW power output was installed in Schopfloch – Germany and finished in October 2021. The development of the installation took 2 months because of a leek of materail.  Together 12 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical installation incl. pile driving

Mounting structure: SL Rack Gmbh

Modules: 450-455W

 

 

 

 

Galéria:

Similar projects

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.