Project Nr. 196

Project Nr. 196

Büttel, Germany, 10000 KWp

Completion date: May, 2021

Power: 10000 KWp

Scope of services: Complete mechanical installation including pile driving

 

Project Nr. 196 with a 39 MW power output was installed in Buttel – Germany  in April/May 2021. The development of the installation took 6 weeks.  Together 30 experienced engineers were part of the installation process.

Solar Company has provided the complete mechanical photovoltaics installation of 10MW pile driving and 6MW frame assembly include modules installations.

Frame manufacturer: Enerparc AG

Galéria:

Similar projects

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.