Project Nr. 356
Land: Lassing, Austria
Fertigstellung: November, 2023
Leistung: 1300 KWp
Leistungsumfang: Komplette mechanische Installation, einschließlich Ziehen von Gleichstromkabeln.
Project Nr. 356 with a 1300 KWp power output was installed in Austria. Assembly works were finished in 4Q 2023. The development of the installation took 2 weeks. Together 12 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation of Alumero frame system including pile driving with GAYK HRE 3000