Project Nr. 347
Land: Mindelstetten, Germany
Fertigstellung: November, 2023
Leistung: 10500 KWp
Leistungsumfang: Komplette mechanische Installation, einschließlich Ziehen von Gleichstromkabeln.
Project Nr. 347 with a 10500 KWp power output was installed in Germany. Assembly works were finished in 4Q 2023. The development of the installation took 8 weeks. Together 30 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation of MKG Gobel frame system including pile driving with GAYK HRE3000