Project Nr. 341
Land: Baia Mare, Romania
Fertigstellung: October, 2023
Leistung: 1400 KWp
Leistungsumfang: Komplette mechanische Installation, einschließlich Ziehen von Gleichstromkabeln.
Project Nr. 341 with a 1400 KWp power output was installed in Romania. Assembly works were finished in 3Q 2023. The development of the installation took 3 weeks. Together 12 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation incl. DC connection.