Project Nr. 323
Land: Poustka, Czech Republic
Fertigstellung: July, 2023
Leistung: 3000 KWp
Leistungsumfang: Komplette mechanische Installation, einschließlich Ziehen von Gleichstromkabeln.
Project Nr. 323 with a 3000 KWp power output was installed in Czech Republic. Assembly works were finished in 3Q 2023. The development of the installation took 3 weeks. Together 12 experienced engineers were part of the installation process. The mounting system was from Energy 5.
Solar Company has provided the mechanical installation including pile driving with GAYK HRE 3000