Project Nr. 320
Land: Unterbinnwang, Germany
Fertigstellung: April, 2023
Leistung: 4800 KWp
Leistungsumfang: Komplette mechanische Installation, einschließlich Ziehen von Gleichstromkabeln.
Project Nr. 320 with a 4800 KWp power output was installed in Germany. Assembly works were finished in 2Q 2023. The development of the installation took 4 weeks. Together 20 experienced engineers were part of the installation process. The mounting system was from SL Rack GmbH.
Solar Company has provided the mechanical installation including pile driving with GAYK HRE 3000