Project Nr. 312
Land: Haselbach, Germany
Fertigstellung: March, 2023
Leistung: 4200 KWp
Leistungsumfang: Komplette mechanische Installation, einschließlich Ziehen von Gleichstromkabeln.
Project Nr. 312 with a 4200 KWp power output was installed in Germany. Assembly works were finished in March 2023. The development of the installation took 3 weeks. Together 20 experienced engineers were part of the installation process. The mounting system was from Schletter.
Solar Company has provided the mechanical installation incl. GAYK pile driving.