Project Nr. 294
Land: Handenberg, Germany
Fertigstellung: November, 2022
Leistung: 3500 KWp
Leistungsumfang: Komplette mechanische Installation, einschließlich Ziehen von Gleichstromkabeln.
Project Nr. 294 with a 3500 KWp power output was installed in Germany. Assembly works were finished in November 2022. The development of the installation took 30 days. Together 12 experienced engineers were part of the installation process. Zimmermann system was used for this solar park.
Solar Company has provided the complete mechanical installation incl. pile driving with GAYK