Project Nr. 265
Land: Ulmu, Romania
Fertigstellung: August, 2022
Leistung: 4200 KWp
Leistungsumfang: Komplette mechanische Installation, einschließlich Ziehen von Gleichstromkabeln.
Project Nr. 265 with a 4,2 MWp power output was installed in Romania. Assembly works were finished in August 2022. The development of the installation took 4 weeks. Together 18 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation incl. pile driving