Project Nr. 237
Land: Auerbach, Germany
Fertigstellung: December, 2021
Leistung: 670 KWp
Leistungsumfang: Komplette mechanische Installation, einschließlich Ziehen von Gleichstromkabeln.
Project Nr. 237 with a 0,67 MW power output was installed in Germany – and finished in December 2021. The development of the installation took 5 days. Together 10 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation.