Project Nr. 235
Land: Flutzholm, Germany
Fertigstellung: December, 2021
Leistung: 6000 KWp
Leistungsumfang: Komplette mechanische Installation, einschließlich Ziehen von Gleichstromkabeln.
Project Nr. 235 with a 6MW power output was installed in Germany – and finished in December 2021. The development of the installation took 3 weeks . Together 40 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation incl. pile driving with two machines GAYK HRE 3000