Project Nr. 217
Land: Schopfloch, Germany
Fertigstellung: October, 2021
Leistung: 3200 KWp
Leistungsumfang:Komplette mechanische Installation include rammen
Project Nr. 217 with a 3200 KW power output was installed in Schopfloch – Germany and finished in October 2021. The development of the installation took 2 months because of a leek of materail. Together 12 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation incl. pile driving
Mounting structure: SL Rack Gmbh
Modules: 450-455W