Project Nr. 213
Land: St. Valentin, Austria
Fertigstellung: August, 2021
Leistung: 1200 KWp
Leistungsumfang: Komplette mechanische Installation, einschließlich Ziehen von Gleichstromkabeln.
Project Nr. 213 with a 1200 KW power output was installed in St. Valentin – Austria and finished in August 2021. The development of the installation took 3 weeks. Together 8 experienced engineers were part of the installation process.
Solar Company has provided the complete mechanical installation incl. DC
Mounting system: PMT